Features:
Target date: late October
Overall status: Oct 29: Release posted.
Line item | Volunteer | Target start date | Target completion date | Status |
---|---|---|---|---|
Overall schema design work | all | July 1 | Aug 31 | Complete |
Infrastructure and framework | Neil Graham, Elena Litani, Sandy Gao | Aug. 24 | Sept. 21 | Complete |
Datatype and msg port | Elena Litani | Aug. 24 | Aug. 31 | Complete |
Schema Handler and document info | Neil Graham | Aug. 24 | Oct. 12 | Complete |
Identity constraint traversal | Neil Graham | Sept. 13 | Sept. 24 | Complete |
SimpleType traversal | Elena Litani | Aug. 24 | Sept. 21 | Complete |
Element traversal | Sandy Gao | Aug. 24 | Sept. 25 | Complete |
Attribute traversal - initial implementation | Sandy Gao | Aug. 24 | Sept. 25 | Complete |
Group traversal | Rahul Srivastava (Elena Litani, Lisa Martin) | Sept. 1 | Sept. 10 | Complete |
wildcard support - initial implementation | Sandy Gao, Rahul Srivastava | Aug. 24 | Sept. 25 | Complete |
Attribute group traversal - initial implementation | Sandy Gao, Rahul Srivastava | Aug. 24 | Sept. 25 | Complete |
Complex type support | Lisa Martin | Sept. 1 | Oct. 5 | Complete |
Schema validator - initial implementation | Sandy Gao | Sept. 4 | Sept. 25 | Complete |
Content models: builder, simple | Elena Litani | Sept. 4 | Sept. 25 | Complete |
Content models: DFA | Neil Graham | Sept. 24 | Oct. 1 | Complete |
Notation traversal | Rahul Srivastava | Sept. 15 | Sept. 18 | Complete |
Misc. AttributeUse, attributeGroup Changes
|
Rahul Srivastava | Oct. 1 | Oct. 5 | Complete |
wildcard utility methods
|
Rahul Srivastava | Oct. 1 | Oct. 19 | Complete |
Schema Validator - identity constraint checking | Neil Graham | Oct. 5 | Oct. 11 | Complete |
Schema Validator - default/fixed element values | Neil Graham | Oct. 5 | Oct. 11 | Complete |
Schema Validator - ENTITY validation | Elena Litani | Oct. 1 | Oct. 19 | Complete. |
Schema resolution changes | Elena Litani | Oct. 1 | Oct. 1 | Complete |
annotation | Pavani Mukthipudi | Sept. 26 | Oct. 1 | Complete |
all Content Model | Pavani Mukthipudi | Sept. 26 | Oct. 4 | Complete |
mixed Content Model | Elena Litani | Sept. 24 | Oct. 1 | Complete |
Testing | all | Oct. 8 | Oct. 22 | Complete. |
Package restructuring | Elena Litani | Oct. 24 | Oct. 25 | Complete |
Configuration changes | Elena Litani, Sandy Gao | Oct. 24 | Oct. 25 | Complete |
Attempt final build and post to apache | all | Oct. 25 | Oct. 31 | Complete
|